As mentioned earlier I am migrating stuff over to a different datacenter in Toronto today. CCF will appear a bit slow and may go down a few times. Part of the plan.
The steps are as follows for those of you that are looking for bedtime reading:
1. Migrate database to Toronto location - DONE as of now
2. Replicate to Montreal (Redundant) - Nov 6 DONE
3. Replicate to Seattle (Mirror) - Nov 8
4. Migrate files and caches to Toronto - Nov 6
5. Replicate to Montreal (Redundant) - Nov 6 DONE
6. Replicate to Seattle (Mirror) - Nov 9
7. Setup High availability load balancers (West) - Nov 10
8. Setup HA LBs (East) - Nov 6 DONE
9. Migrate domain records - Kicked off today IN PROGRESS
10. Kickoff Geographical Redundant monitors - Nov 12
11. Try to break it a bunch of times - Nov 12
12. Run another logo competition - Nov 13
So all in all by Nov 12th we should be fully geographically redundant as well as being fully redundant within our datacenters.
Blah blah blah....
The steps are as follows for those of you that are looking for bedtime reading:
1. Migrate database to Toronto location - DONE as of now
2. Replicate to Montreal (Redundant) - Nov 6 DONE
3. Replicate to Seattle (Mirror) - Nov 8
4. Migrate files and caches to Toronto - Nov 6
5. Replicate to Montreal (Redundant) - Nov 6 DONE
6. Replicate to Seattle (Mirror) - Nov 9
7. Setup High availability load balancers (West) - Nov 10
8. Setup HA LBs (East) - Nov 6 DONE
9. Migrate domain records - Kicked off today IN PROGRESS
10. Kickoff Geographical Redundant monitors - Nov 12
11. Try to break it a bunch of times - Nov 12
12. Run another logo competition - Nov 13
So all in all by Nov 12th we should be fully geographically redundant as well as being fully redundant within our datacenters.
Blah blah blah....